Starship Development Thread #47

SpaceX Starship page

FAQ

  1. When (first) orbital flight? First integrated flight test occurred April 20, 2023. "The vehicle cleared the pad and beach as Starship climbed to an apogee of ~39 km over the Gulf of Mexico – the highest of any Starship to-date. The vehicle experienced multiple engines out during the flight test, lost altitude, and began to tumble. The flight termination system was commanded on both the booster and ship."
  2. Where can I find streams of the launch? SpaceX Full Livestream. NASASpaceFlight Channel. Lab Padre Channel. Everyday Astronaut Channel.
  3. What's happening next? SpaceX has assessed damage to Stage 0 and is implementing fixes and changes including a water deluge/pad protection/"shower head" system. No major repairs to key structures appear to be necessary.
  4. When is the next flight test? Just after flight, Elon stated they "Learned a lot for next test launch in a few months." On April 29, he reiterated this estimate in a Twitter Spaces Q&A (summarized here), saying "I'm glad to report that the pad damage is actually quite small," should "be repaired quickly," and "From a pad standpoint, we are probably ready to launch in 6 to 8 weeks." Requalifying the flight termination system (FTS) and the FAA post-incident review will likely require the longest time to complete. Musk reiterated the timeline on May 26, stating "Major launchpad upgrades should be complete in about a month, then another month of rocket testing on pad, then flight 2 of Starship."
  5. Why no flame diverter/flame trench below the OLM? Musk tweeted on April 21: "3 months ago, we started building a massive water-cooled, steel plate to go under the launch mount. Wasn’t ready in time & we wrongly thought, based on static fire data, that Fondag would make it through 1 launch." Regarding a trench, note that the Starship on the OLM sits 2.5x higher off the ground than the Saturn V sat above the base of its flame trench, and the OLM has 6 exits vs. 2 on the Saturn V trench.


Quick Links

RAPTOR ROOST | LAB CAM | SAPPHIRE CAM | SENTINEL CAM | ROVER CAM | ROVER 2.0 CAM | PLEX CAM | NSF STARBASE

Starship Dev 46 | Starship Dev 45 | Starship Dev 44 | Starship Dev 43

Official Starship Update | r/SpaceX Update Thread


Status

Road Closures

Type Start (UTC) End (UTC) Status
Primary 2023-08-04 13:00:00 2023-08-05 01:00:00 Possible
Alternative 2023-08-06 13:00:00 2023-08-07 01:00:00 Possible
Alternative 2023-08-07 13:00:00 2023-08-08 01:00:00 Possible

Up to date as of 2023-08-04

Vehicle Status

As of July 28th 2023

Follow Ring Watchers on Twitter and Discord for more.

Ship Location Status Comment
S15 Rocket Garden Scrapped
S20 Rocket Garden Retired
S24 Gulf of Mexico Destroyed Destroyed on during Flight Test 1
S25 Launch Site Testing Spin Prime and Static Fire
S26 Rocket Garden Resting No fins or heat shield, plus other changes.
S27 Rocket Garden Scrapped Common dome imploded
S28 Rocket Garden Pending Raptor install Previously tested at Masseys
S29 High Bay 1 Under construction
S30 Build Site Under construction
S31 Build Site Parts under construction Assorted parts spotted through S34.

 

Booster Location Status Comment
Pre-B7 & B8 Scrapped or Retired B4 is in the Rocket Garden, the rest are scrapped.
B7 Gulf of Mexico Destroyed Destroyed April 20th in Flight Test 1
B9 Mega bay Pending raptor swap and hot-stage ring install Static fire (August 5th)
B10 Masseys Testing Cryo testing
B11 Rocket Garden Resting
B12 Megabay Raceways installed
B13 Build Site Parts under construction
B14 Build Site Parts under construction
B15 Build Site Parts under construction


Resources

557 comments
  • New comment from /u/santacfan on Reddit:

    Starbase live-

    1:54am- LR11000 disconnected from the y pipe

    2:51am- Little crane lifts what appears to be a stand out of the pit

    2:57am- What looks like a short piece of pipe is lifted into the pit

    3:51am- Stand lowered into the pit

    4:00am- LR11000 swings over and lowers it’s hook into the pit

    4:39am- Grover lifts more rebar over for the cryo pit lid

    4:50am- Another load of rebar is moved over

    4:58am- 3rd load of rebar moved. That’s going to be one beefy lid

    9:42am- Grover lifts what may be one of the extra deluge plate extensions over to the gap by the new stairs

    9:59am- Swung back over to the side and sat down

    10:07am- Grover lowers

    11:14am- Concrete being cut

    11:15am- Grover shows off and swings the extension plate back over to the OLM while lowered.

    11:38am- Plate lowered. Lines go slack.

    11:40am- Raised back up

    11:47am- Lowered back down

    11:57am- Picked back up and swung off to the side again

    12:53pm- Generator removed from the pit

    1:24pm- Basket goes up

    1:31pm- LR11000 unhooks from whatever it was attached to (Most likely the Y pipe)

    1:33pm- Basket goes down

    2:07pm- Grover starts to remove it’s counter weights to move (Maybe to Masseys to lift B10?)

    2:13pm- Grover removes more weights

    2:18pm- More weights moved over to an SPMT

    2:23pm- There goes another

    2:24pm- LR11000 takes tension on its lifting straps

    2:38pm- LR11000 lifts another deluge pipe. Grover removed 4 more weights

    2:41pm- Pipe is raised higher and swung over OLM

    2:48pm- Pipe starts lowering

    2:58pm- Pipe is sat on the ground and the LR11000 is unhooked

    2:59pm- Small crane hooks to the pipe

    3:05pm- Pipe is swung over towards the left most manifold. So looks like it’s the left side of the Y. If the piece lifted early this morning was the right side, this should be the last piece to go around the OLM. Now we need the 2 feed pipes from the concrete bunker over.

    3:05pm- At the same time, Grover lowers.

    3:38pm- Grover drives away

    4:43pm- The LR11000 drives away from the OLM

    5:35pm- Small crane moves into the area that the LR11000 was sitting

    7:34pm- Chopsticks lowered. Indicating all of the big lifts on the right side and behind the OLM are finished

    8:04pm- Extension piece (?) lifted back over towards the OLM.

    11:00pm- Pretty quiet evening from what we can see. I’m sure the welders are hard at work. I’ll be watching for more rebar to go in the pit to signify that they are done and the pipes are ready to be buried.

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    12:57am- Short piece of pipe lifted into the pit

    7:27am- Rebar lifted over by the deluge area. No idea where this is going. Maybe just staging it for the OLM pit?

    7:33am- More rebar lifted

    7:40am- Possible metal imbed lifted

    7:43am- Another imbed. Square piece of metal

    7:49am- Another imbed. 90 degree angle piece

    7:52am- Crane moving the rebar lowers

    9:15am- Large straight rebar lifted over to the pit

    9:22am- More rebar

    10:26am- Crane on left side disconnects from whatever it was supporting. (Most likely the small section of pipe that was lifted in last night)

    11:00am- Left crane lifts something into the pit. Can’t tell what it is

    11:09am- Deluge pipe lifted over. Has to be one of the feed pipes coming in from the bunker.

    11:47am- LR11000 lifts large metal frame to the ship QD. Looks like it went to the little side wing

    1:09pm- More rebar lifted over

    1:15pm- More rebar

    1:26pm- More rebar

    2:03pm- LR11000 goes for a walk

    2:15pm- More rebar

    2:24pm- Long reach excavator tamps down bottom of pit

    2:54pm- More rebar

    3:08pm- LR 11000 arrives next to S25

    3:14pm- Load of scaffolding pieces lowered to the top of the OLM

    3:31pm- More rebar moved

    3:34pm- LR11000 picks up the squid

    3:39pm- More rebar swung over

    3:48pm- Squid swung over to S25

    3:55pm- Lift goes up at S25

    4:01pm- Workers start connecting the squid

    4:22pm- Squid connected

    4:23pm- Crane lowers something between OLM and OLT. Can’t see what though

    4:43pm- Grover goes up in the background and moves 3 loads. Looks like the counterweight tray and 2 more counterweights

    5:05pm- More rebar

    5:45pm- Crane on the left side lifts deluge feed pipe and repositions it

    6:20- Lift goes up at S25

    6:29pm- Deluge pipe lifted out and sat by side of pit. Workers gather around the end

    6:36pm- Lift at S25 goes down

    6:37pm- Lift goes up to Chopsticks, near pivot point by the tower

    6:43pm- Deluge pipe lifted back into the pit

    6:49pm- Forklift drives under OLM

    7:06pm- Appears to have another one of the plate extensions. Goes between cryo pipe leg and new stairs leg

    7:39pm- Disconnected from the forklift

    8:45pm- Scaffolding and tarps being set up under the OLM. The great weldathon continues.

    9:15pm- Grover moves back closer to the deluge tank farm and starts lifting counterweights back on

    10:02pm- Grover finishes stacking counterweights and turns towards the water deluge tank farm

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    11:50pm- Lift that had been up at the chopsticks goes down

    11:56pm- Lift goes back up to the chopsticks

    12:00am- Lift goes back down

    1:48am- Lift goes back up to the chopsticks

    4:11am- Lift goes back down

    6:29am- Basket up top of OLM

    6:45am- 2nd segment of the 4th level of the new high bay lifted

    7:01am- Basket down

    7:30am- Basket up to the door at the top of the new stairs

    7:31am- Large L shaped metal object (I think it’s a small diameter pipe) lowered into the pit

    7:40am- Basket down

    7:50am- Basket up top of OLM

    8:19am- 2 lifts go up to the side of S25

    8:33am- Basket down

    8:53am- Basket up to the door

    9:26am- Basket goes down

    11:03am- Large L shape pipe that was lowered earlier is repositioned

    11:55am- Lift goes back up to the chopsticks

    12:21pm- Zoom in on the crew working on the chopsticks. Seem to be working on the hydraulics for the stabilizer arm

    12:34pm- Looks like they removed the hydraulic ram

    12:44pm- Lift moves over to the other side of the stabilizer arm

    1:05pm- Lifts go down at S25. Access hatch is open and vent tube installed

    2:25pm- Lift back up at S25

    3:38pm- Square piece of metal lifted to the top of the OLM

    4:35pm- Concrete pump truck seen in background. Checked Nerdle cam and it looks like it was pouring around the high pressure tanks for the deluge earlier and now it’s over by the old landing pad.

    4:40pm- Another piece of metal lifted to the top of the OLM

    5:33pm- Pumper truck folds up to leave

    6:12pm- Lift goes up to top of chopsticks

    6:33pm- 2nd lift goes up to the stabilizer arm

    6:46pm- First lift goes down

    7:03pm- 1 of the lifts at S25 goes down

    7:07pm- Lift at the stabilizer arm goes down. No sign of a new hydraulic piston

    7:16pm- Both lifts go back up

    7:25pm- Top lift goes back down. Looks like they are just inspecting

    7:51pm- Lift at the stabilizer arm goes down. Was working in the piston area but SBL zoomed out and went on a tour

    9:18pm- Lift goes up to the side of the drawworks shed. Whoever was hoping that they would replace the shielding soon might be in luck.

    10:03pm- Lift at the drawworks goes down. There was definitely sparks flying like they were starting to cut something.

    10:46pm- Lift was back at the drawworks shed. Looks like they tried a different method of cutting and then went back down

    11:00pm- Concrete pump truck arrives at the right side of the cryo pipe pit. Time to finally pour it’s lid?

    11:05pm- Pump unfolds

    12:07pm- First concrete truck is at the pump and the arm folds out towards the far side of the cryo pipe trench. The lid it is.

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase Live-

    1:12am- S25 starts rolling

    1:20am- Turns on to Hwy 4

    2:08am- Turns on to to Remidos

    2:19am- Arrives at the rocket garden

    7:32am- Sheriff at road block

    7:52am- FireX test

    8:07:20- Deluge test/system prime

    8:09am- Pope stack starts venting

    8:15:33- Igniter test

    8:29am- Grid fin tests

    8:50am- NSF going live

    9:42am- Booster venting it’s ambient pressure

    10:35am- Sub coolers are off. Working a problem in the OTF?

    10:39am- Workers head to pad/ Roadblock still in place

    10:42am- Ship puck shucker headed back to Masseys

    11:00am- Workers at the generator by the Lox sub coolers

    11:04am- Pope stack firing back up

    11:32am- Workers starting to leave pad

    11:35am- All 3 vehicles leave. Pad clear again

    11:44am- Lox subcoolers going again

    12:15pm- OLM vent

    12:53pm- Frost forming on the methane sub coolers

    1:01pm- Waterfall mode on the OLM vent. We’re getting close to fueling

    1:03pm- OLM vent stopped. Prop load should be underway. Around 90 minutes to test possibly

    1:06pm- Engine chill underway

    1:08pm- New engine cavity purge vents going

    1:09pm- Frost forming quickly

    1:10pm- Lox chill pit active

    1:18pm- Methane frost line forming

    2:02pm- Drone

    2:05pm- OLM vent. Loading complete

    2:08pm- FireX / Deluge / Fire (Lots of steam)

    2:10:30- Deluge stops

    2:12pm- Depress vent

    2:41pm- Pad looks good but they are going to need some new fencing

    3:17pm- Engine compartment and Deluge plate purge

    3:47pm- Another purge from the new engine compartment vents

    3:53pm- Big depress vent (That should be it)

    4:55pm- OLM vent

    5:00pm- Road open

    6:16pm- OLM vent finally ends

    7:59pm- 3 SPMT’s headed to launch site with counterweights and connectors. B9 coming back?

    8:04:32pm- SPMT down! Looked like a hydraulic failure? Front went up, back all the way down and to the left where the weight was. They got it leveled back out and going pretty quick though.

    9:22pm- Workers return to pad

    9:28pm- 3 workers kneel down to look at one spot on the plate

    9:48pm- After checking the rest of the pad, they came back for a second look at the one spot

    10:15pm- Workers headed up the stairs to check the inside of the OLM

    10:21pm- Exit the OLM and drive away

    10:52pm- Lift goes back up at OLM (New door)

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    12:36am- Lift goes up to the stabilizer arm again

    12:47am- Lift goes down

    1:26am- Lift back up at the draw works shed. Sparks flying

    2:02am- Lift go up to S25

    2:43am- Lift at S25 goes down

    3:47am- Lift at the draw works goes down. About half done.

    5:20am- Pump truck folds up. Pour done

    6:54am- Lift back up at the draw works shed

    8:08am- Lift goes back down. About 3/4 done.

    8:11am- New medium lift crane arrives at the right side of OLM

    8:18am- Lift back up at S25 and right back down after a few minutes

    8:53am- Piece of equipment lifted to the top of the OLM. (Blue, boxed shape, not quite sure what it was)

    9:06am- Lift goes back up to the draw works

    9:13am- Another piece of equipment is lifted to the bottom of the Cryo pipe leg.

    9:47am- 2 lifts go up to S25

    9:55am- Small rectangular piece of metal lifted to the top of the OLM

    10:14am- Piece of metal that was just lifted is removed

    10:21am- Lift at the draw works goes down

    10:31am- Lift goes back up

    10:32am- Piece of metal goes back up. Needed some fine tuning?

    10:41am- Similar shaped piece gets lifted up

    10:55am- 3rd piece of metal goes up

    11:15am- Piece of pipe lifted up to the new door

    11:34am- Another piece of pipe goes up

    11:42am- Lifts go down at S25

    11:58am- Lift at the draw works goes down

    12:16pm- Lift goes back up at S25

    1:16pm- Lift goes back up to the draw works shed

    3:30pm- Short piece of metal beam lifted to the top of the OLM.

    3:57pm- Basket goes up to the new door

    4:05pm- Basket goes down

    4:41pm- Lift at the draw works shed goes down. Looks like all of the damaged siding is now removed. (Took a total of 9 hours and 44 minutes to remove it)

    5:26pm- Forklift lowers sheet of metal into the deluge feed pipe pit

    7:24pm- Purge of the deluge pressure system

    8:03pm- Lifts at S25 have gone down

    8:04pm- Next mega bay section and booster stand are on the move

    8:19pm- Cop at the roadblock? Stopped traffic long enough for the booster stand to move down Hwy 4 and turn on Eichorn

    8:37pm- Booster stand went over for storage by the raptor install stand

    8:47pm- Lifts go back up to S25

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase Live-

    11:50pm- Lift goes up to chopsticks. Work continues on the stabilizer arms

    1:23am- Blue box looking piece of equipment that was lifted to the top of OLM yesterday is brought back down

    2:33am- Concrete pump truck goes up and extends between OLM and OLT

    3:28am- Tarp goes up at the draw works shed. Sparks fly. It looks like some of the cross beams are being removed

    8:15am- The boom on the concrete pumper has not moved since it was set up

    8:36am- Big section of black tarp set up at the base of the OLM

    9:01am-Boom on the concrete pumper retracts some

    9:36am- Zoom in on the end of the pump truck boom shows it in the deluge pipe pit

    10:10am- Pumper truck retracts

    10:16am- Workers back up at the damaged water tank shell. Yeah the tank doesn’t exactly sit flush with the straight edge they hold up

    10:28am- Pumper truck extends back out

    10:35am- Basket goes up too top left side

    12:34pm- Pump boom is all the way over by the 3rd manifold. They may be finishing up the concrete under the OLM.

    12:50pm- Back up working on the stabilizer arms

    1:50pm- Pump truck folds up

    2:10pm- New crossbeam is being risen to the draw works shed

    3:02pm- You can see all 3 access hatches on S25 have been opened

    4:09pm-Zoomed in shot shows that the concrete is up to the top of the wooden forms around the OLM

    4:25pm- It looks like they may have back filled over the deluge feed pipes and now they’re just trying to work on the correct grade

    4:57pm- Forklift brings in what looks like a giant toy top to a work station set up by the OLT

    5:32pm- Forklift removes some large hoses from same work station

    6:11pm- Forklift lifts a circular hatch. Moves it to the other side of the OLT

    6:35pm- 3 lifts up at the access hatch to S25’s methane tank

    7:30pm- Upper cross brace removed from the draw works shed

    7:53pm- Cutting torch comes out at the shed

    8:58pm- Sparks flying, welders welding. Slow day for cranes and lifts but no doubt lots of work is still getting done.

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase Live-

    (Tornado= Raptor QD Spin up test)

    11:21:21pm- Tornado

    11:35pm- Small (No tornado)

    11:40:45pm- Tornado

    11:55:13pm- Small (No tornado)

    12:08:19am- Tornado

    12:31:14am- Tornado

    1:01:04am- Tornado

    1:16:54am- Small (No tornado)

    1:19:37am- Tornado

    1:52:47am- Tornado

    1:55am- Depress vent?

    3:56am- Workers back at pad

    8:50am- Crane lifts a bunch of boards out from beside the OLM

    9:15am- Basket goes up. Center

    9:33am- Crane lifts something with a lot of cables hanging off of it

    5:25pm- Lots of people working on top of the OLM but the cranes and lifts have been silent today

    6:00pm- Intermittent closure starts. NSF in SBL chat says that Jack is reporting sheriffs at the launch site. So maybe more testing instead of something moving?

    6:20pm- Pope stack is venting (Going back and looking, I’m pretty sure it was just the pope stack and not the OLM like people were saying)

    7:00pm- Seems like a full test/purge of the cryo lines

    7:08pm- Can’t tell if that’s the new purge line or if there is just a massive leak

    7:20pm- Launch site cloaking device engaged

    7:29:10- People were reporting a bang. I can hear a slight pop but NSF’s mic is so far away that I don’t know if I’d put much faith in it being anything.

    7:30pm- Venting seems to be letting up some

    7:34pm- Pope stack is going again

    8:00pm- Still venting. Seems to die off some and then pick back up

    8:30:42- Sounds like a cell phone ringing. So I think you have to discount all of the bangs and pops

    9:28:53- Drone comes out of lox cloud

    10:36pm- Really starting to die off. Tank finally getting empty?

    10:53pm- Down to a trickle at the beach but still a significant cloud by the actual tanks

    11:16pm- Vent still going but small enough for people to return to the pad and people to leave the beach

    Rover 2-

    20:43:40- Something is definitely wrong. 4 person red team shows up in 2 carts and makes their plans on how they are going to punch thru and get to the big lox tank and spin the shutoff valve. Stick together and get out if the monitor goes off. The banging and popping sounds like a warning klaxon on here.

    21:08- One guy walks out and a pick up shows up

    21:10- Pick up leaves the pad

    21:12- 2 more guys walk out on their cell phones

    21:32- 47 minutes later, I’m going to guess they couldn’t get the valve to shut.

    21:51- Lots of honking. It seems people are trapped on the beach.

    21:54- Lab switches R2’s feed to R3 and we lose the microphone

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    11:07pm- 2 fondag trucks

    11:13pm- Grinding over in the draw works shed

    11:27pm- Shower of sparks off the OLM

    12:40am- 5 Fondag trucks

    3:07am- Excavator leaves. 7 trucks

    5:49am- Dog house is moved next to the crane

    7:47am- Workers shoveling dirt out of the dog house

    8:37am- Straps attached to the dog house

    8:40am- Forklift with more rebar on the right side of the OLM

    9:15am- Lift up at S15

    9:30am- Aerial work platform arrives between OLM and OLT

    9:54am- More formwork is going up between the OLM and the retention pond

    10:30am- Crane lifts doghouse and flips it over

    10:54am- Doghouse re rigged and lifted

    11:03am- Crane carried it over and lowered it back in place at the bottom of the cryo pipe lid

    11:42am- Pump truck is up over at the old landing pad area

    12:56pm- 3rd piece of shielding goes up in the left side of the stairs

    1:10pm- Pump truck folds up

    1:36pm- Excavators digging to the left of the pad that was just poured. Looks like they are making a dirt ramp beside the edge of the concrete so it’s not a 3ft drop off.

    1:44pm- Pump truck goes back up by the retention pond. End of boom goes behind the OLT

    1:52pm- Paint crew is back at it

    2:13pm- Pump truck folds up again

    3:54pm- Lift up at the lower left side skid of the chopsticks

    4:04pm- Forklift lifts metal plate over towards the data cable leg

    4:15pm- Crew back up at B9’s methane tank

    7:27pm- RIP SN15. You proved to the world it was possible and paved the way for all that is to come. Your legend will live on when the story of starship is told.

    9:07pm- Forklift brings over another inspection hole cover plate to the data cable leg

    9:18pm- 3rd inspection plate brought over

    9:32pm- 4th plate

    9:43pm- 5th plate

    10:05pm- Crane lifts a piece of plastic pipe up on to the OLM from the dirt off to the side. One worker then picks it up and drags it off to the side

    10:21pm- Crane lifts a remote controlled trench roller up onto the OLM from same area as pipe

    10:56pm- There’s just something about a shower of sparks flying off the top of the OLM at night that makes me smile.

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    12:26am- Pump truck goes up behind OLM. Swings over to the pit

    2:16am- First concrete truck arrives on Rover 2

    2:28am- Boom starts moving around

    7:00am- We’re at 40 trucks so far.

    7:21am- Pump truck folds up

    7:28am- Another pump truck is arriving

    7:53am- 2nd pump truck going up

    8:14am- 2nd pump truck folds up(?). Concrete trucks going straight to the back side of the pit

    9:48am- Crane lifts an acetylene torch from over by the pit to the front side of the OLM

    10:06am- Crane lifts a load of rebar away from the pit

    10:26am- Crane lifts an air compressor over to the pit

    10:50am- 45 trucks so far and it looks like that may be it. Of interest, it seemed like the pump truck last night never got the area over by the crane. Fully expected that the 2nd pump truck would set up to reach that area but it didn’t.

    (That puts my rough count at 560 concrete truck loads so far)

    11:08am- 2nd pump truck goes back up

    11:30am- Pump truck goes back down

    11:35am- Pump truck leaves the OLM.

    1:21pm- PA announcement- Attention on the orbital pad, due to B9 check outs on the launch mount, expect loud venting. Hearing protection is recommended

    1:24:50pm- Venting

    2:48pm- Visitors under the OLM

    3:03pm- Times to get those legs looking spiffy. The paint crew is back

    7:39pm- Forklift brings in a piece of metal sheeting and lifts it up towards the draw works shed

    9:15pm- Next section of the new mega bay being rolled over for lift

    9:46pm- Dance floor is lowering

    10:06pm- Crane swings in another light tower to the OLM

    10:25pm- Swings another light tower over towards the pit

    10:34pm- Dance floor is completely down

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    7:50am- No lights went on last night and I still don’t see any workers on or around the OLM.

    8:14am- Vehicles start pulling up at the OLM

    8:20am- Lift goes up to S25

    9:09am- Starting to bring equipment back in.

    9:16am- Raptor install platform looks like it’s going back together after being cut in half last week

    10:07am- Dance floor goes back up

    10:32am- Pump truck arrives to the back side of the pit. (Will today be the day they finish the pour?)

    10:35am- They’ve got themselves a nice new big scissor lift.

    10:44am- Pump truck goes up

    11:05am- Third ventilation hose being installed

    11:35am- Concrete pour starts

    12:30pm- 10 trucks so far. Looks like they are pouring at the new retention pond

    1:35pm- 14 trucks

    1:46pm- Ventilation hose extended up to the booster

    1:52pm- New SQD extends for the first time on hoop cam

    2:40pm- 18 trucks

    3:22pm- SQD retracts

    3:31pm- 22 trucks

    4:40pm- 25 trucks

    5:04pm- Concrete pump truck starts to fold up. Worked on the retention pond and the spillway over towards it.

    5:09pm- Workers start to remove the access hatch into B9

    7:21pm- Hatch to the lox tank is opened

    9:07pm- Workers appear to be getting ready to enter B9. Just put ladder in through the hatch

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase live-

    10:52pm- More rebar to the pit

    1:46am- Something was tested on the OLM

    2:34am- Yep more rebar. (Pretty quiet night except for work in the pit)

    3:08am- More rebar into the pit. Long reach excavator appears done with the concrete

    4:17am- Forklift brings a generator over to the pit area

    4:19- B9 rolls down Remidos to Hwy 4

    4:55am- Rebar work continues around the deluge pipe pit in the cryo leg area

    6:14am- Forklift brings in a new light tower and blinds view under the OLM

    6:29am- B9 starts rolling

    7:29am- B9 turns into the launch site

    7:42am- A giant rocket rolling in isn’t going to stop the rebar work

    7:45am- B9 arrives at the pad

    7:54am- Chopsticks start rising

    7:59am- Chopsticks open

    8:12am- Booster moves closer to lift area

    8:24am- Chopsticks lower into lift position

    8:31am- More rebar lifted over

    8:50am- B9 moves in between chopsticks

    9:06am- Basket lifted up to the top of the OLM

    9:30am- Basket lowered

    9:36am- Square Piece of equipment lifted off the top

    9:41am- Piece of equipment lifted out of the pit

    9:45am- More rebar lifted over

    10:18am- More rebar. They’re really pushing on it today

    10:29am- Yep another batch of rebar. The next concrete pour has to be coming soon

    10:56am- Crane moves to right side of the OLM and lifts a rebar cage structure. Moves it over by the new stairs. I’d assume just staging for later. Then crane moves back to left side.

    11:21am- Rebar

    11:23am- PA announcement- Overhead drone work

    12:05pm- Workers up at the base of B9

    12:15pm- Pad clearing

    12:23pm- Chopsticks closing around B9

    12:28pm- Closing in tighter to latch on

    12:33pm- Starting to raise up to the pins

    12:54pm- Sounds like the drone that warned Jack the other day is out warning people again today

    1:03pm- Ship 28 moves to the entrance of the high bay

    1:37pm- Clamps on the stand retracting from booster

    2:02pm- LR11000 lowering at the build site. Most likely being reconfigured to finish building the new mega bay

    2:06pm- One of the tall aerial work platforms arrives at the launch site

    2:10pm- Workers climbing on to the stand

    2:18pm- (14:18) Rover 2- Sounds like somebody’s radio by the camera. Lift will be attempted again in 2 hours.

    2:20pm- Looks like some of the clamps are stuck?

    2:23pm- Aerial work platform goes up to the top of the booster

    2:30pm- Workers climbing on top of B9

    2:46pm- When you got some unexpected free time, you grab a broom and try to get rid of some of that dust

    3:00pm- Aerial work platform comes down

    3:27pm- Workers back on top of the OLM

    3:58pm- Workers climbing off B9’s stand. Finally unstuck?

    4:02pm- Ship 28 lifted in the high bay

    4:08pm- Pad clearing again. Looks like 5 people still working on the booster

    5:30pm- Stabilizer arms going in

    5:48pm- One guy still walking around on the stand

    6:31pm- People are back on top of the OLM. Not looking good for the lift. The stand appears to be afraid to let B9 go after seeing what happened to B7.

    8:10pm- It moved!!!

    8:11pm- S28 unhooked from the bridge crane

    8:17pm- Clamps releasing

    8:27pm- Clears the stand

    8:34pm- Stabilizer arms going in once again

    8:37pm- Drone up

    8:54pm- Guide pins retract back into the stand

    8:55pm- Up we go at a good pace and then it paused

    9:00pm- That SpaceX drone has quite the spotlight

    9:04pm- Booster is rotating

    9:06pm- Going up again

    9:09pm- Clears the OLM. Pauses. Drone checking underside of the booster

    9:11pm- Starts rotating over the pad

    9:18pm- Starting to lower

    9:27pm- Engines starts going below the lip of the OLM

    9:32pm- Drone checking out one of the skates on the right side of the chopsticks

    9:45pm- Engines below the lip of the OLM. Making final adjustments

    Rover 1-

    16:47- New puck shucker is rolled in under Ship 28

    17:05- S28 touches down on stand

    (This gets synced)

  • New comment from /u/santacfan on Reddit:

    Starbase Llive-

    3:13am- Work starts back up

    4:31am- Crane picks up a light tower from in front of the OLM and swings it over to the pit on the left side

    5:08am- They are using the long reach excavators bucket to move concrete from a delivery truck to the gaps between the legs and the manifolds

    5:12am- Crane swings a load of long straight rebar over to the pit

    5:32am- Crane swings another load of rebar over to the pit

    6:49am- Final segment of the 4th level of the new mega bay is lifted

    7:45am- More rebar lifted over to the pit

    8:08am- Another load of rebar, looks like one more load sitting there waiting.

    8:23am- Workers carrying sticks of rebar over to the area between the cryo pit lid and the OLM. Other workers appear to be getting more of the gaps between the legs and manifolds ready for concrete

    9:23am- Load of rebar lifted to the pit

    9:38am- Pump truck goes up by the new cryo pit

    9:40am- Crane lifts a big ball of what looks like twisted metal out of the pit. Ghost of SN11?

    10:24am- Workers up at the SQD

    10:58am- More rebar lifted over

    11:04am- Yep you guessed it, more rebar

    11:31am- Even more rebar. (When we saw the wire mesh mats lifted over yesterday, I thought they were close to done. I was wrong)

    1:34pm- Rebar magically continues to appear out of no where. (Okay it was probably just a new delivery )

    1:36pm- Worker on top of the chopsticks looking at the rail

    2:23pm- Crane lifts black object over to the pit

    4:04pm- Pump truck folds up

    4:22pm- Crane lifts a load of supplies off of the top of the OLM

    4:35pm- Crane lifts another load off the top

    4:38pm- More rebar lifted over to the pit

    4:56pm- 3rd load off the top of the OLM. (Maybe the scaffolding out of the center? There are people climbing around on the scaffolding on the top but it doesn’t look like they are actually taking anything apart)

    6:10pm- Lift up looking at the cameras at the end of the stabilizer arms

    7:19pm- Second crane comes in and lifts what looks to be a new dog house and sits it off to the side. Looks longer like the one for the cryo leg.

    7:44pm- Second crane leaves. Doesn’t look like it’s going to install the new doghouse

    8:55pm- 2 people back up working on the SQD

    9:00pm- Gravel being dumped over by the pit on the left side. Just outside of the form work.

    9:10pm- Long reach excavator returns. Looks like it’s dumping concrete between the legs and manifolds again.

    9:25pm- Definitely doesn’t look like they are preparing for any testing tonight.

    9:45pm- I may have spoke to soon. Pad starting to clear out some. There are still people welding, grinding, and people over in the pit though

    10:14pm- More rebar lifted into the pit

    (This gets synced)